Solar Blue's systems are top of the line products. They require attention to detail and a lot of work in order for the systems to be in top shape and function as efficiently as possible. Our Installation process spans the course of 4 days* where our technicians will go from the initial meeting, the delivery of the product, to the installation, and final testing.

 

  • Contractor and representatives of all subcontractors shall meet at the Property in an area designated by MRHC.
  • Systems will be delivered to site.
  • Materials will be moved into the area of installation (Tanks, panels, skids, pipes, etc)
  • If any items can be installed on the ground then they will be (I.E – Hot Water Skid Systems)
  • Prepping of any plumbing with current hot water system.
  • If a crane is needed, they will be on site for moving materials on the roof. By the 1st day all material should be on the roof so the crane does not need to return.
  • Roofers shall prepare the roof mounts as the system is held on the roof by the crane. Once a place has been marked, the roofer can begin work.
  • The Units will be secured to the roof of the Building.
  • Contractor and representatives of all subcontractors shall meet at the Property in an area designated by MRHC.
  • Roofers will perform final roof prepping of the mounts.
  • If roofer has not done so on the first day, he will seal mounts to ensure that roof warranty is not voided.
  • If Core Drilling is needed, he will do so now by the new hot water tanks.
  • Once core drilling is done, roofer will seal the hole.
  • The foregoing will occur four (6) times (six (6) Units).
  • All Units will begin being connected and monitoring systems will be started to be installed.
  • Contractor and representatives of all subcontractors shall meet at the Property in an area designated by MRHC.
  • Monitoring systems will continue to be installed and tested.
  • Plumbing will continue connecting the systems.
  • Insulation will cover all copper piping
  • “Peel and Curl” insulation will be applied over all insulation until the piping runs to the ground.
  • Water will be introduced into the solar hot water system.
  • Contractor and representatives of all subcontractors shall meet at the Property in an area designated by MRHC.
  • “Wrap-up” of any items not done such as piping or wiring.
  • Walk though for clean up of roof, remove all garbage items introduced from our company.
  • SolarBlue will coordinate the connection of the System to the Property’s current natural gas water heating system.
  • SolarBlue will coordinate the recheck of the entire System including, but not limited to, all mounts and plumbing.
  • SolarBlue and Hi-Tech will conduct further tests of the System during the remainder of the day.
* This is an estimate only. Installation time may vary depending on conditions and building type.
 